328/3338–12FE Reference Handbook 10.4 · Civil · Construction · Scheduling

Handbook formula

PERT Expected Time and Variance

Beta approximation: mean te and σ from optimistic/most-likely/pessimistic. Path variance is Σσ² along a path (independence). P(finish) from z=(T−Σte)/√Σσ².

Optimistic, most likely, pessimistic
Expected duration

Step-by-step solved example

to=4, tm=6, tp=14 days. te and σ?

1234TF = LS − ES
Three times on an activity: to, tm, tp → te, σ.
  1. 1. te

    (4+24+14)/6=7.0 d.

  2. 2. σ

    (14−4)/6=1.67 d.

Answer: te=7 d, σ=1.67 d

10 practice questions

0/10 correct

1.If to=tm=tp=5, te=

2.Variance of an activity is

3.Critical path in PERT uses

4.Two sequential σ=2 and 3: σ_path=

5.z= (T−μ)/σ with μ=Σte

6.to=2, tm=3, tp=4: te=

7.PERT is more useful than CPM when

8.A large (tp−to) means

9.Finish probability 84% is about

10.Merge bias means