Step-by-step solved example
T1=10 h, 90% curve. Time of the 8th unit? (8=2³)
1. b
log0.9/log2= −0.1522.
2. T8
Three doublings: 10×0.9³=7.29 h.
Answer: T8 = 7.29 h
T1=10 h, 90% curve. Time of the 8th unit? (8=2³)
1. b
log0.9/log2= −0.1522.
2. T8
Three doublings: 10×0.9³=7.29 h.
Answer: T8 = 7.29 h
1.80% curve is
2.r=1 means
3.Unit 4 on a 90% curve from T1 is
4.b is negative because
5.Crew change / layoff often
6.T1=8 h, 80% , n=2: T2=
7.Cumulative time for n units is not n×Tn because
8.log r / log 2 for r=0.9 is nearest
9.Prefabrication that repeats 100 times is a good
10.A 70% curve from 12 h: 8th unit (3 doublings) is