314/3338–12FE Reference Handbook 10.4 · Construction · Scheduling

Handbook formula

CPM Total Float

Forward pass: ES + duration = EF; ES of a following activity is the max EF of predecessors. Backward pass: LS = LF − duration. Total float is the time an activity can slip without delaying the project. Free float is slip without delaying a successor’s ES.

Early start / early finish
Late start / late finish
(days)
Total float

Step-by-step solved example

Activity C: predecessors A (EF=4) and B (EF=6), duration 5, project LF through C is 14. Find ES, EF, LS, TF.

1234TF = 0 on critical path
Activity-on-node: TF = LS − ES. Critical when TF = 0.
  1. 1. Forward

    ES = max(4,6) = 6. EF = 11.

  2. 2. Backward

    LF = 14, LS = 9. TF = 9 − 6 = 3 d.

Answer: ES=6, EF=11, LS=9, TF=3 d

10 practice questions

0/10 correct

1.A critical activity has

2.Project duration equals

3.Free float is always

4.Crashing a project means

5.FS relationship means

6.ES = 10, duration = 4. EF =

7.If all paths but one have float, the critical path is

8.A dummy activity in AOA networks

9.PERT expected duration te =

10.LS = 12, ES = 7. TF =