Step-by-step solved example
1 loader, t_load = 2 min, 4 trucks each t_truck = 10 min. MF?
1. Plug in
MF = (4 × 2) / (1 × 10) = 0.80.
2. Read
MF < 1 → loader waits a bit; trucks are slightly few or cycles long.
Answer: MF = 0.80
1 loader, t_load = 2 min, 4 trucks each t_truck = 10 min. MF?
1. Plug in
MF = (4 × 2) / (1 × 10) = 0.80.
2. Read
MF < 1 → loader waits a bit; trucks are slightly few or cycles long.
Answer: MF = 0.80
1.MF = 1 means
2.MF > 1 typically means
3.Nt = 5, tl = 3, Nl = 1, tt = 15. MF =
4.Adding trucks increases
5.Longer haul increases t_truck and
6.Match factor is dimensionless because
7.Two loaders in the formula sit in
8.Optimum MF on real jobs is often
9.If t_load = 0 the formula gives
10.Fleet matching is a