Step-by-step solved example
Activity D=5, ES=8. This activity’s LF = 16. TF?
1. EF
EF = 8+5 = 13.
2. LS
LS = 16−5 = 11.
3. TF
TF = LS−ES = 11−8 = 3 (also 16−13=3).
Answer: TF = 3
Activity D=5, ES=8. This activity’s LF = 16. TF?
1. EF
EF = 8+5 = 13.
2. LS
LS = 16−5 = 11.
3. TF
TF = LS−ES = 11−8 = 3 (also 16−13=3).
Answer: TF = 3
1.Critical path activities have TF =
2.EF =
3.LS =
4.Two predecessors finish at 4 and 7. Successor ES =
5.Free float is
6.A dummy has D =
7.If TF = 5 and you delay the activity 7 days the project
8.Backward pass starts from
9.LS < ES would mean
10.Two successors with LS = 12 and 15. Predecessor LF =