Unit-price contracts pay actual quantities at bid unit prices. Unbalancing (high p on early/overrun items) can be legal but unethical if it misleads. Lump-sum is one price for the defined scope.
qi
Estimated quantity
pi
Unit price
Step-by-step solved example
Excavation 8000 CY @ $12, concrete 200 CY @ $400. Bid? If excavation is 9000 CY, payment extra?
Unit prices × quantities = bid; actual q pays the contract.
1. Bid
8000×12+200×400=96000+80000=$176,000.
2. Overrun
1000×12=$12,000 extra (if the spec pays overruns at unit price).
Answer: Bid $176,000; +$12,000 if 1000 CY extra excavation
10 practice questions
0/10 correct
1.A lump-sum overrun of scope is handled by
2.Unbalancing front-loads cash by
3.If you expect a quantity overrun you might
4.3 items: 10×5 + 4×20 + 8×10 =
5.Engineer’s estimate is
6.A responsive bid meets
7.Payment quantity from average-end-area is
8.Retainage withholds
9.If actual q=0 for an item, payment is
10.Ethics: an unbalanced bid intended to exploit a known owner error is