325/3338–12FE Reference Handbook 10.4 · Construction · Mass haul

Handbook formula

Mass-Haul Diagram

Mass diagram plots cumulative cut (+) / fill (−) vs station. Balance points where the curve returns to the previous extremum. Freehaul is the specified free distance; overhaul is pay beyond that, in station-yards or m³·stations.

Earth volume
Freehaul distance

Step-by-step solved example

1000 bcy hauled 800 ft; freehaul=500 ft. Overhaul station-yards? (1 sta=100 ft)

cutfillstations
Haul volume × station distance; freehaul vs overhaul.
  1. 1. Overhaul distance

    800−500=300 ft = 3.0 stations.

  2. 2. Pay

    Overhaul=1000×3.0=3000 sta-yd.

Answer: 3000 station-yards

10 practice questions

0/10 correct

1.A rising mass curve is

2.Balance point is where

3.Freehaul is

4.Overhaul is paid on volume × extra distance beyond

5.A valley in the mass diagram (below a balance line) is

6.Waste is

7.Borrow is

8.Average haul for a mass loop is

9.Swell must be applied when

10.Stations on the x-axis are