Step-by-step solved example
PV = $80k, EV = $70k, AC = $90k. CPI, SPI, CV?
1. CPI
CPI = 70/90 = 0.778 (over budget).
2. SPI
SPI = 70/80 = 0.875 (behind).
3. CV
CV = 70 − 90 = −$20k.
Answer: CPI = 0.78, SPI = 0.88, CV = −$20k
PV = $80k, EV = $70k, AC = $90k. CPI, SPI, CV?
1. CPI
CPI = 70/90 = 0.778 (over budget).
2. SPI
SPI = 70/80 = 0.875 (behind).
3. CV
CV = 70 − 90 = −$20k.
Answer: CPI = 0.78, SPI = 0.88, CV = −$20k
1.CPI > 1 means
2.SPI < 1 means
3.SV =
4.EV = 50, AC = 50, PV = 40. The job is
5.EAC ≈ BAC/CPI is used when
6.BAC is the
7.CV = +10 k means
8.If EV = PV = AC the project is
9.Percent complete (cost) ≈
10.SPI does not use