317/3338–12FE Reference Handbook 10.4 · Construction · Scheduling / cost

Handbook formula

Earned Value Indices

EV earned value, AC actual cost, PV planned value. CPI < 1 over budget; SPI < 1 behind schedule. CV and SV are differences with the same meaning. Estimate at completion EAC ≈ BAC/CPI if the overrun persists.

Earned value
Actual cost
Planned value

Step-by-step solved example

PV = $80k, EV = $70k, AC = $90k. CPI, SPI, CV?

P12345An
EV, PV, and AC as time-phased money like a cash-flow diagram.
  1. 1. CPI

    CPI = 70/90 = 0.778 (over budget).

  2. 2. SPI

    SPI = 70/80 = 0.875 (behind).

  3. 3. CV

    CV = 70 − 90 = −$20k.

Answer: CPI = 0.78, SPI = 0.88, CV = −$20k

10 practice questions

0/10 correct

1.CPI > 1 means

2.SPI < 1 means

3.SV =

4.EV = 50, AC = 50, PV = 40. The job is

5.EAC ≈ BAC/CPI is used when

6.BAC is the

7.CV = +10 k means

8.If EV = PV = AC the project is

9.Percent complete (cost) ≈

10.SPI does not use