Qualifications-based selection (QBS)≻price-only bidding for PE services
NSPE and Brooks Act (federal A/E) prefer qualifications-based selection: rank firms on competence, then negotiate a fair fee. Price-only bidding for professional engineering can pressure unsafe under-scoping. After award, do not bid-shop subconsultants unethically. Advertising must be truthful.
QBS
Qualifications first, fee second
Brooks Act
Federal A/E procurement model
Step-by-step solved example
A city wants sealed dollar bids only for a dam's engineering, no SOQ. An NSPE-minded PE should?
1. Issue
Price-only selection of engineering for a high-hazard dam invites inadequate investigation.
2. Response
Advise the city toward QBS (Brooks-style). If they insist, the PE may decline a price-only proposal that would force unsafe shortcuts — public safety still governs.
Answer: Recommend QBS; do not under-scope a dam to win a price war.
10 practice questions
0/10 correct
1.QBS means
2.Price-only competition for PE design is discouraged because it
3.The Brooks Act applies primarily to
4.After a fair QBS award, bid-shopping the design fee downward by reopening competition is
5.Construction competitive bidding (for contractors) is
6.Advertising 'we are the cheapest PE stamp in the state' is
7.A PE may ethically submit a fee proposal when
8.Under-scoping a geotechnical investigation to win the fee
9.Selection committees should weigh
10.If a public owner is legally required to take low bid for professional services, the PE should