Step-by-step solved example
Want vs=0.025 m/s sand. Chamber Q=0.4 m³/s. Minimum plan A?
1. vo=vs
A=Q/vs=0.4/0.025=16 m².
2. Note
Provide more A and a controlled vh (channel grit).
Answer: A ≥ 16 m²
Want vs=0.025 m/s sand. Chamber Q=0.4 m³/s. Minimum plan A?
1. vo=vs
A=Q/vs=0.4/0.025=16 m².
2. Note
Provide more A and a controlled vh (channel grit).
Answer: A ≥ 16 m²